Which task constraint ensures that a task is scheduled for a specific three-day window?

Prepare for the Adobe Workfront Exam with our quiz. Use flashcards and multiple choice questions, each with detailed explanations and tips. Ace your test!

The choice of Fixed Dates is accurate because this constraint is specifically designed to lock a task within a predetermined time frame. When a task is assigned Fixed Dates, it indicates that the task must start and finish within a specified set of dates, ensuring it occurs in that specific three-day window. This is particularly useful for tasks that are time-sensitive or dependent on external deadlines.

Using Fixed Dates helps project managers maintain control over the timeline of a project and provides clarity on when resources should be allocated to that task. It creates a sense of urgency and helps ensure that tasks do not extend beyond the defined period.

The other options represent different types of constraints that do not define a strict three-day scheduling window. For example, As Soon As Possible allows a task to start as soon as resources are available but does not restrict it to a specific timeframe. Must Finish On ensures a task is completed by a particular date but does not dictate a start date, and Start No Earlier Than allows a task to start after a certain date, which can extend beyond the three-day window.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy