What should a project manager use if they want to track the number of requests in Adobe Workfront that have been converted?

Prepare for the Adobe Workfront Exam with our quiz. Use flashcards and multiple choice questions, each with detailed explanations and tips. Ace your test!

The project manager should use a conversion report to track the number of requests that have been converted in Adobe Workfront. This type of report is specifically designed to provide insights into the conversion process, allowing users to see how many requests have successfully moved from one status to another, such as from a request to a project.

A conversion report typically contains key metrics and data points that highlight trends over time, making it easier for project managers to analyze their team's performance regarding request conversions. It allows for effective oversight and decision-making, supporting the overall management process.

Using a project report would not be as effective for this purpose since project reports generally focus on broader project performance metrics, timelines, resources, and overall progress, rather than the specific conversion stats for requests. Thus, while a project report can be useful for monitoring aspects of project management, it does not provide the focused insights needed to track request conversions specifically.