What is the projected completion date for a task with a Planned Start Date of July 24, and a Must Finish on constraint with a duration of 5 days?

Prepare for the Adobe Workfront Exam with our quiz. Use flashcards and multiple choice questions, each with detailed explanations and tips. Ace your test!

The projected completion date for a task with a Planned Start Date of July 24 and a Must Finish On constraint with a duration of 5 days is determined by calculating the number of workdays from the Planned Start Date.

Starting from July 24, and counting 5 working days, the sequence would be as follows: July 24 (Day 1), July 25 (Day 2), July 26 (Day 3), July 27 (Day 4), leading to the completion of the task on July 28 (Day 5). The Must Finish On constraint ensures that the task must be completed by a specific date, but since the task timeline starts on July 24 and includes working days, July 28 becomes the actual date of completion.

Therefore, the informed answer for the projected completion date is July 28, indicating that while the task begins on July 24, workdays must be considered in context with the duration specified to arrive at the correct completion date.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy