If a project is not complete and the planned completion date of the project is in the past, what is the progress status of the project in Adobe Workfront?

Prepare for the Adobe Workfront Exam with our quiz. Use flashcards and multiple choice questions, each with detailed explanations and tips. Ace your test!

When a project in Adobe Workfront is not complete and its planned completion date has already passed, the appropriate progress status for that project is "Late." This term is used to indicate that the project has missed its originally established deadline and is not on track to be completed as initially planned.

In project management terms, labeling a project as "Late" helps stakeholders quickly assess that action may be needed to address the delays. This can involve reallocating resources, revising timelines, or communicating with team members about next steps. It's a clear, unambiguous way to convey the urgency of the situation when the project has not yet been finalized, signaling that the timeline is behind expectations.

Other terms like "In Trouble," "Behind," or "On Schedule" may not accurately reflect the status of the project in this context. "In Trouble" is often used for more severe situations, while "Behind" is a more general term that does not specifically denote a missed deadline. "On Schedule" clearly implies that a project is progressing as planned, which contradicts the situation described in the question. The specificity of the term "Late" makes it the most appropriate choice in this scenario.