A task has a Completion Date of December 16 with a duration of 10 days. When set automatically, what is the Planned Start Date?

Prepare for the Adobe Workfront Exam with our quiz. Use flashcards and multiple choice questions, each with detailed explanations and tips. Ace your test!

To determine the Planned Start Date based on the Completion Date and the duration of the task, you need to count backward from the Completion Date. The Completion Date is December 16, and the task's duration is 10 days.

When you calculate the Planned Start Date, you subtract the duration from the Completion Date. This involves counting back 10 days from December 16, which brings you to December 6. Therefore, the Planned Start Date is indeed December 6, as it accurately reflects the starting point necessary to complete the task within the given duration.

Understanding this calculation process is crucial in project management, as it helps ensure that timelines are correctly aligned and that tasks are scheduled efficiently within the overall project timeline.