A Project Manager needs to know the Planned Variance for the copywriters on a project. Which steps should be taken to show the Planned Variance for the month?

Prepare for the Adobe Workfront Exam with our quiz. Use flashcards and multiple choice questions, each with detailed explanations and tips. Ace your test!

The correct answer involves using the Utilization Tab to filter by the job role of copywriter and setting the date range to the current month. This approach allows the Project Manager to obtain a clear view of the planned variance specifically for the copywriters during the relevant timeframe in question.

By filtering for the copywriter job role, the Project Manager can focus on the pertinent resources involved in this project, as planned variance is usually assessed on the specific roles contributing to project tasks. Additionally, by setting the date range to the current month, the Project Manager can accurately analyze performance data, resource allocation, and actual work completed against what was originally planned, thereby revealing any discrepancies or variances.

Choosing options with specific references such as $$TODAYbm or $$TODAYem may lead to confusion as they imply using specific coding or expressions that could be subjective to variance interpretations and may not necessarily reflect the intended date range effectively. Setting the date range to last month would not align with the requirement to assess the current month's planned variance. Thus, focusing on the current month is essential for timely decision-making and performance evaluation.