A Project Manager is reviewing a task that has a Planned Start Date of July 20, a Planned Completion Date of July 24, and a "Must Finish On" constraint with a Duration of 5 days. What is the projected completion date for this task?

Prepare for the Adobe Workfront Exam with our quiz. Use flashcards and multiple choice questions, each with detailed explanations and tips. Ace your test!

To determine the projected completion date for the task with a "Must Finish On" constraint, it is essential to understand how this constraint influences the scheduling of the task. The "Must Finish On" constraint indicates that the task must be completed by a specific date, which is July 24 in this scenario.

Given that the task has a Planned Start Date of July 20 and a Duration of 5 days, one would typically add the duration to the start date to calculate the completion date. Starting on July 20 and accounting for 5 days of work (including weekdays and potentially excluding weekends, depending on the organization's calendar settings), the direct addition would yield July 24 as the completion date.

Since the task must finish on or before July 24, this aligns perfectly with the planned timeline. Therefore, the projected completion date for the task is indeed July 24, as stipulated by both the planned dates and the "Must Finish On" constraint. This ensures that the project management parameters are adhered to efficiently, leading to timely task delivery.